Progress on North Main Avenue

North Main Avenue is nearing having it’s final grade with many truckloads brought in the past few weeks.  When completed, the pavement will be more than ten feet higher than the old roadbed, placing this street well above any past flood levels.  There still needs to be a 2 inch pressure sewer installed in the street which will provide sewage from the wildlife refuge.  One of the employees of the contractor said that they may get curbs installed this week and possibly paving  done before Thanksgiving.   However, he said it would be more likely the first week of December.

We’re all looking forward to the completion of this project which began  after July 4th week-end.